The government of Alberta has tabled legislation that would restrict the construction of artificial intelligence (AI) data centres close to homes or some farmland, while imposing measures to limit water use and protect electricity customers from additional costs.
Bill 42, the Energy, Environment and Utilities Statutes Amendment Act, was introduced Nov. 18. It proposes a minimum distance of 600 metres between residential properties and data centres that use 10 megawatts or more of electricity.
The bill would also establish new oversight of water consumption and electricity infrastructure costs.
Data centres house servers that store and process digital information, while AI data centres are designed to handle the more intensive computing demands of artificial intelligence systems.
The Alberta government said the proposals in Bill 42 followed four public town halls held in August and September, along with a survey of Albertans and other public feedback on the expansion of AI data centres.
“Albertans told us what matters most: their communities, farmland and water. We listened,” Minister of Technology and Innovation Nate Glubish said in a Nov. 18 press release.
“These proposed rules would make sure AI data centres grow in Alberta on Alberta’s terms, with clear protections for communities and the certainty investors need to build here.”
The legislation comes as Alberta positions itself as an AI infrastructure hub. A November report from the Information and Communications Technology Council estimated that 78 to 92 percent of Canada’s planned data centre development is slated to take place in the province.
Opposition to AI Data Centre Expansion
Proposed AI data centres have faced opposition in several Alberta communities, with residents voicing concerns about water consumption, noise, environmental impact, electricity costs, and skepticism about promised economic benefits.
In August, the Alberta Utilities Commission (AUC) rejected an application by Synapse Real Estate Corp. to build a natural gas power plant to help power a proposed AI data centre campus in the small town of Olds, Alta. The commission said the site was too close to residential areas and the developer had not demonstrated why that proximity was necessary.
Approximately 1,500 parties applied to participate in the regulatory process as intervenors, with many objecting to the planned AI data centre campus.
Opposition has also arisen over Meta’s planned $13-billion AI data centre campus in Sturgeon County north of Edmonton, which broke ground on July 8.
Dozens of protesters demonstrated outside county offices on Aug. 2, raising concerns over the project’s potential impact on local water supplies, electricity costs, and the environment.
Rocky View County, near Calgary, also voted in July to temporarily pause its consideration of new data centre proposals as it works to develop clearer rules for the industry.
Changes in the Bill
Under Bill 42, large data centre projects would need to be approved by the Alberta Utilities Commission, which currently regulates power plants and electricity infrastructure linked to the data centres but not the centres themselves.
The commission would also oversee requirements involving noise, lighting, heat recovery, water use, and farmland protection, as well as electricity-related measures intended to prevent infrastructure costs from being passed on to customers.
The proposed 600-metre setback from homes would allow exceptions. Municipalities could apply to the commission for different distances where local planning supports such development.
The bill would also restrict construction of large data centres on what it terms “high-quality agricultural land” saying this specific category could be specifically defined in future regulations.
The legislation adds that the provincial cabinet would still have a veto and could “by order, approve the construction or operation of a data centre on designated high-quality agricultural land.”
Although the government has proposed stronger oversight of water consumption, the legislation does not specify numerical water-use limits. Those details would be established through subsequent regulations, with the bill stating that the government will prioritize data centre development at industrial sites, brownfield sites, and locations that already have power generation facilities available.
Electricity Prices
Section 2 of the bill would amend the province’s Electric Utilities Act and says that electricity rates “must not include the costs associated with a transmission facility that forms a part of a designated data centre system.”
The proposed changes build on legislation passed in December 2025 which already required data centre developers to cover necessary transmission upgrades rather than passing those costs on to ratepayers.
Another provision in the bill gives the provincial government authority to make rules on how much electricity data centres are permitted to use and to order them to reduce usage to avoid strain on Alberta’s electricity grid.